STEPS INVOLVED ACTIONS OF THE OFFICE OF THE MUNICIPAL ENGINEER TRANSACTION TIME PERSON/S RESPONSIBLE
Submit the necessary requirements for the application of a Building Permit, w/ duly accomplished Building Permit Form Receives and evaluates the validity of the documents 30 minutes Engineering Personnel
Accompany the Field Inspector in the inspection of the site/construction Conducts inspection

Evaluates proper building setback incorporated in the plan and actual site condition.

10 minutes Building Inspector
Accomplish the Application Form Processes and evaluates the correctness of the Building Permit 5 minutes Engineering Personnel
Bring one (1) set of building plans and cost estimate to the Bureau of Fire Protection Evaluates the documents and gives order of payment for the Fire Safety Protection Fee 5 minutes Municipal Fire Marshall
Submit one (1) set of building plans and cost estimate to the MPDC Evaluates the documents and gives order of payment for Zoning Fee 5 minutes Municipal Planning and Development Coordinator
Proceed to the Bureau of Fire Protection to secure a Fire Safety Protection Certificate Issues a Fire Safety Protection Certificate 3 minutes Fire Safety Inspection
Bring the OR for

Zoning fee to the

Office of the MPDC.

Issues Zoning Certificate 2 minutes MPDC staff
Get the order of

payment for the

Building Permit Fee

from Office of the

STEPS INVOLVED ACTIONS OF THE OFFICE OF THE MUNICIPAL ENGINEER TRANSACTION TIME PERSON/S RESPONSIBLE
Accompany the Electrical Inspector in the inspection of the site/project Conducts inspection 20 minutes Engineering personnel
Submit the complete requirements and accomplish the Wiring Permit Form Processes and evaluates the correctness of the requirements and assess the fees 10 minutes Engineering Personnel
Proceed to the Office of the Municipal Treasurer for payment (Staff of the Office of the Municipal Treasurer receives the payment and issues Official Receipt) 3 minutes Revenue Collection Clerk/Staff
Present the OR to the Building Official Documents and OR will be recorded 5 minutes Building Official
Wait for the release of the Electrical Wiring Permit Issues the Electrical Permit 5 minutes Building Official

Municipal Engineer Releases order of payment 3 minutes Building Official

Proceed to the

Office of the

Municipal Treasurer

for payment

(Staff of the Office of the Municipal Treasurer receives the payment and issues Official Receipt) 3 minutes Revenue Collection Clerk/staff
Present OR to the

Municipal Engineer

and wait for the

release of the permit

Documents will be recorded thereafter, a Building Permit will be released 10 minutes Building Official

ABOUT THE SERVICE A Building Permit is a document issued by the Building Official to an owner/applicant to proceed with the construction, installation, addition, alteration, renovation, conversion, repair, demolition or other work activity of a specific project/building/structure after the accompanying principal plans and specifications and other pertinent documents that are found satisfactory and substantially confirming with the Implementing Rules and Regulations of the National Building Code.

CLIENT GROUP General Public

REQUIREMENTS ->Accompanied prescribed application forms

->Barangay Clearance

->Clearance from the Homeowners’ Association (if any)

->Official Receipt of payment for Fire Safety Inspection Fee

->Official Receipt of payment for Zoning Fee

->In case the applicant is the registered owner of the lot:

-Photocopy of TCT

-Photocopy of Tax Declaration

-Photocopy of Current Real property Tax Receipt

->In case the applicant is not the registered owner of the lot,

in addition to the above is a copy of a duly notarized

Contract of Lease or Deed of Absolute Sale

->5 sets each of the following Ancillary Plans and Documents:

-Bill of Materials and Cost Estimates

-Specifications

-Civil/Structural Plan/Soil Testing (3 Storey Structure Up)

-Electrical Plan

-Sanitary/Plumbing

-Architectural Plan

-Geodetic Documents if necessary

-Mechanical Plan, if necessary

->Photocopy of the PRC ID of duly registered professionals

who signed the accomplished Building Permit forms

FEES/PAYMENT REQUIRED Only the Building Official can give the Order of Payment for the Building Permit Fee depending on the plans and specifications as well as the Cost Estimates submitted by the applicant/owner

SERVICE SCHEDULE Monday to Friday

8:00 am – 5:00 pm

TOTAL PROCESSING TIME 1 hour and 16 minutes

PROCESS OF AVAILING THE SERVICE

STEPS INVOLVED ACTIONS OF THE OFFICE OF THE MUNICIPAL ENGINEER TRANSACTION TIME PERSON/S RESPONSIBLE
Submit the necessary requirements for the application of a Building Permit, w/ duly accomplished Building Permit Form Receives and evaluates the validity of the documents 30 minutes Engineering Personnel
Accompany the Field Inspector in the inspection of the site/construction Conducts inspection

Evaluates proper building setback incorporated in the plan and actual site condition.

10 minutes Building Inspector
Accomplish the Application Form Processes and evaluates the correctness of the Building Permit 5 minutes Engineering Personnel
Bring one (1) set of building plans and cost estimate to the Bureau of Fire Protection Evaluates the documents and gives order of payment for the Fire Safety Protection Fee 5 minutes Municipal Fire Marshall
Submit one (1) set of building plans and cost estimate to the MPDC Evaluates the documents and gives order of payment for Zoning Fee 5 minutes Municipal Planning and Development Coordinator
Proceed to the Bureau of Fire Protection to secure a Fire Safety Protection Certificate Issues a Fire Safety Protection Certificate 3 minutes Fire Safety Inspection
Bring the OR for

Zoning fee to the

Office of the MPDC.

Issues Zoning Certificate 2 minutes MPDC staff
Get the order of

payment for the

Building Permit Fee

from Office of the

Municipal Engineer

Releases order of payment 3 minutes Building Official
Proceed to the

Office of the

Municipal Treasurer

for payment

(Staff of the Office of the Municipal Treasurer receives the payment and issues Official Receipt) 3 minutes Revenue Collection Clerk/staff
Present OR to the

Municipal Engineer

and wait for the

release of the permit

Documents will be recorded thereafter, a Building Permit will be released 10 minutes Building Official

ISSUANCE OF CERTIFICATE OF BUILDING COMPLETION

AND CERTIFICATE OF OCCUPANCY

ABOUT THE SERVICE A Certificate that certifies the completion of the project with the knowledge that meets the standards of the Implementing Rules and Regulations of the National Building Code. The building/structure can now be utilized as a public edifice or private residence which is now safe for occupancy.

CLIENT GROUP General Public

REQUIREMENTS ->Fire Safety Inspection Certificate

->As Built-Plan

->Photocopy of the Building Permit

->Certificate of Completion for Construction Form

FEES/PAYMENT REQUIRED Only the Building Official can give the Order of Payment for the Certificate of Occupancy depending on the building and Final Cost Estimated submitted. (COCC)

SERVICE SCHEDULE Monday to Friday

8:00 am – 5:00 pm

TOTAL PROCESSING TIME 35 minutes

PROCESS OF AVAILING THE SERVICE

STEPS INVOLVED ACTIONS OF THE OFFICE OF THE MUNICIPAL ENGINEER TRANSACTION TIME PERSON/S RESPONSIBLE
Secure Final Fire Safety Protection Certificate Endorsement by the Building Official to the Bureau of Fire Protection 3 minutes Fire Safety Inspection
Inspection Inspection Report of the Bldg. 20 minutes Bldg. Inspector
Submit all necessary requirements Evaluates and processes the documents 5 minutes Engineering Personnel
Proceed to the Office of the Municipal Treasurer for payment (Staff of the Office of the Municipal Treasurer receives the payment and issues Official Receipt) 3 minutes Revenue Collection Clerk/Staff
Present OR to the Building Official Documents and OR will be recorded 2 minutes Building Official
Wait for the release of the OCC Issues Certificate of Occupancy 2 minutes Building Official

ISSUANCE OF ELECTRICAL WIRING PERMIT AND

CERTIFICATE OF ELECTRICAL COMPLETION

ABOUT THE SERVICE An Electrical Wiring Permit is a requirement for installing, replacing, removing, connecting, disconnecting or repairing electrical works except replacing fuses, receptacles, switches and utilization equipment. On the other hand, a Certificate of Electrical Completion formally marks the completion of the project where the electrical inspector had inspected and agreed with the proper installation of electrical wirings.

CLIENT GROUP General Public

REQUIREMENTS ->Barangay Clearance

->Lot Owner’s Consent if lot is not owned by the applicant

->Photocopy of TCT

->Photocopy of the latest Real Property Tax Receipt

->Affidavit from the Mayor’s Office if the lot is a government property

->Waiver to be notarized if the lot is not owned by the applicant

->Electrical plans

->Duly accomplished Wiring Permit Form

FEES/PAYMENT REQUIRED For Residential Application & Business Application

->Application fee

->Building fee

->Electrical fee

->Plumbing fee

->Inspection fee

SERVICE SCHEDULE Monday to Friday

8:00 am – 5:00 pm

TOTAL PROCESSING TIME 43 minutes

PROCESS OF AVAILING THE SERVICE

STEPS INVOLVED ACTIONS OF THE OFFICE OF THE MUNICIPAL ENGINEER TRANSACTION TIME PERSON/S RESPONSIBLE
Accompany the Electrical Inspector in the inspection of the site/project Conducts inspection 20 minutes Engineering personnel
Submit the complete requirements and accomplish the Wiring Permit Form Processes and evaluates the correctness of the requirements and assess the fees 10 minutes Engineering Personnel
Proceed to the Office of the Municipal Treasurer for payment (Staff of the Office of the Municipal Treasurer receives the payment and issues Official Receipt) 3 minutes Revenue Collection Clerk/Staff
Present the OR to the Building Official Documents and OR will be recorded 5 minutes Building Official
Wait for the release of the Electrical Wiring Permit Issues the Electrical Permit 5 minutes Building Official

ISSUANCE OF CERTIFICATE OF FINAL ELECTRICAL INSPECTION

ABOUT THE SERVICE A Certificate issued by the Building Official to the owner/applicant as a requirement for the installation of power lines to a building/structure and certifies the completeness of the installation of all electrical wirings.

CLIENT GROUP General Public

REQUIREMENTS ->Photocopy of the Building Permit (Wiring Permit)

->Certificate of Electrical Inspection to be accomplished

by an Electrical Engineer/Master Electrician

->Certificate of Fire Safety

FEES/PAYMENT REQUIRED Assessed by Building official

SERVICE SCHEDULE Monday to Friday

8:00 am – 5:00 pm

TOTAL PROCESSING TIME 8 minutes

PROCESS OF AVAILING THE SERVICE

STEPS INVOLVED ACTIONS OF THE OFFICE OF THE MUNICIPAL ENGINEER TRANSACTION TIME PERSON/S RESPONSIBLE
Submit the complete requirements Evaluates and processes the requirements and assessed fee 1 minute Engineering Personnel
Proceed to the Office of the Municipal Treasurer for payment (Staff of the Office of the Municipal Treasurer receives the payment and issues Official Receipt) 3 minutes Revenue Collection Clerk/Staff
Present the OR to the Building Official Documents and OR will be recorded 2 minutes Building Official
Wait for the release of the CFEI Issuance of the Certificate 2 minutes Building Official

ISSUANCE OF SIGN PERMIT

ABOUT THE SERVICE This permit is issued by the Building Official to regulate the installation of signage displayed for exterior observance so as to show harmonious and aesthetic relationship of all units represented.

CLIENT GROUP General Public

REQUIREMENTS Sketch/drawing indicating the following:

->Complete dimension of the signage

->Number of signage to be displayed

->Location

->Brgy. Clearance

FEES/PAYMENT REQUIRED Payment shall be based upon the sketch/drawing submitted

SERVICE SCHEDULE Monday to Friday

8:00 am – 5:00 pm

TOTAL PROCESSING TIME 14 minutes

PROCESS OF AVAILING THE SERVICE

STEPS INVOLVED ACTIONS OF THE OFFICE OF THE MUNICIPAL ENGINEER TRANSACTION TIME PERSON/S RESPONSIBLE
Submit the complete requirements Receives and evaluates the requirements including Brgy. clearance 5 minutes Building Official/ Engineering Personnel
Accomplish the Sign Permit Form Processes the application form 2 minutes Engineering Personnel
Proceed to the Office of the Municipal Treasurer for payment (Staff of the Office of the Municipal Treasurer receives the payment and issues Official Receipt) 3 minutes Revenue Collection Clerk/Staff
Present the OR to the Building Official Documents and OR will be recorded 2 minutes Building Official
Wait for the permit to be released Issuance of the Sign Permit 2 minutes Building Official

ISSUANCE OF DEMOLITION PERMIT

ABOUT THE SERVICE This permit certifies that the building is structurally unsafe and otherwise constitutes a hazard to safety of health or public welfare because of inadequate maintenance and therefore is declared dangerous to human life and must be demolished.

CLIENT GROUP General Public

REQUIREMENTS ->Barangay Clearance

->Sketch/drawing of the bldg. to be demolished

->Photocopy of TCT where bldg. was constructed

FEES/PAYMENT REQUIRED Payment shall be based upon the sketch/drawing submitted

SERVICE SCHEDULE Monday to Friday

8:00 am – 5:00 pm

TOTAL PROCESSING TIME 17 minutes

PROCESS OF AVAILING THE SERVICE

STEPS INVOLVED ACTIONS OF THE OFFICE OF THE MUNICIPAL ENGINEER TRANSACTION TIME PERSON/S RESPONSIBLE
Submit the complete requirements Receives and evaluates the requirements 5 minutes Building Official/ Engineering Personnel
Accomplish the Demolition Permit Form Processes the application fee 3 minutes Engineering Personnel
Proceed to the Office of the Municipal Treasurer for payment (Staff of the Office of the Municipal Treasurer receives the payment and issues Official Receipt) 3 minutes Revenue Collection Clerk/Staff
Present the OR to the Building Official Documents and OR will be recorded 3 minutes Building Official
Wait for the Permit to be released Issues of the Demolition Permit 3 minutes Building Official

ISSUANCE OF FENCING PERMIT

ABOUT THE SERVICE A requirement for the construction of fences which are greater than 3 feet in height, measured from the finished grade which are also 10 feet of any street right of way or access easement or within 20 feet of a corner.

CLIENT GROUP General Public

REQUIREMENTS ->Barangay Clearance

->Photocopy of TCT

->Sketch/drawing

->Location Map – for Fencing Permit

->Clearance from Assessor’s Office

FEES/PAYMENT REQUIRED Payment shall be based upon the dimension of the fence

SERVICE SCHEDULE Monday to Friday

8:00 am – 5:00 pm

TOTAL PROCESSING TIME 14 minutes

PROCESS OF AVAILING THE SERVICE

STEPS INVOLVED ACTIONS OF THE OFFICE OF THE MUNICIPAL ENGINEER TRANSACTION TIME PERSON/S RESPONSIBLE
Submit the complete requirements Receives and evaluates the requirements 5 minutes Building Official/ Engineering Personnel
Accomplish the Fencing Permit Form Processes the application fee 1 minute Engineering Personnel
Proceed to the Office of the Municipal Treasurer for payment (Staff of the Office of the Municipal Treasurer receives the payment and issues Official Receipt) 3 minutes Revenue Collection Clerk/Staff
Present the OR to the Building Official Documents and OR will be recorded 3 minutes Building Official
Wait for the permit to be released Issuance of the Fencing Permit 2 minutes Building Official

ISSUANCE OF GROUND PREPARATION & EXCAVATION PERMIT

ABOUT THE SERVICE A requirement for the ground preparation & excavation permit.

CLIENT GROUP General Public

REQUIREMENTS ->Barangay Clearance

->Photocopy of TCT

->Sketch/drawing

->Location Map

->Clearance from Assessor’s Office

FEES/PAYMENT REQUIRED Payment shall be based upon the dimension of the lot to be excavated

SERVICE SCHEDULE Monday to Friday

8:00 am – 5:00 pm

TOTAL PROCESSING TIME 14 minutes

PROCESS OF AVAILING THE SERVICE

STEPS INVOLVED ACTIONS OF THE OFFICE OF THE MUNICIPAL ENGINEER TRANSACTION TIME PERSON/S RESPONSIBLE
Submit the complete requirements Receives and evaluates the requirements 5 minutes Building Official/ Engineering Personnel
 Accomplish the Ground Preparation & Excavation Permit Form Processes the application fee 1 minute Engineering Personnel
Proceed to the Office of the Municipal Treasurer for payment (Staff of the Office of the Municipal Treasurer receives the payment and issues Official Receipt) 3 minutes Revenue Collection Clerk/Staff
 Present the OR to the Building Official Documents and OR will be recorded 3 minutes Building Official
Wait for the permit to be released Issuance of the Ground Preparation & Excavation Permit 2 minutes Building Official

Municipal Engineering Office
Engr. Emilnor B. Pasion
Municipal Engineer
Contact number: (02) 651-3155