ABOUT THE SERVICE

This permit is issued by the Building Official to regulate the installation of signage displayed for exterior observance so as to show harmonious and aesthetic relationship of all units represented.

 

CLIENT GROUP                       General Public

 

REQUIREMENTS                     Sketch/drawing indicating the following:

->Complete dimension of the signage

->Number of signage to be displayed

->Location

->Brgy. Clearance

 

FEES/PAYMENT REQUIRED   Payment shall be based upon the sketch/drawing submitted

 

SERVICE SCHEDULE             Monday to Friday

8:00 am – 5:00 pm

 

TOTAL PROCESSING TIME     14 minutes

 

PROCESS OF AVAILING THE SERVICE

 

STEPS INVOLVED

 

 

ACTIONS OF THE OFFICE OF THE MUNICIPAL ENGINEER

 

 

TRANSACTION TIME

 

PERSON/S RESPONSIBLE

Submit the complete requirements Receives and evaluates the requirements including Brgy. clearance 5 minutes Building Official/ Engineering Personnel
Accomplish the Sign Permit Form Processes the application form 2 minutes Engineering Personnel
Proceed to the Office of the Municipal Treasurer for payment

 

(Staff of the Office of the Municipal Treasurer receives the payment and issues Official Receipt) 3 minutes Revenue Collection Clerk/Staff
Present the OR to the Building Official

 

Documents and OR will be recorded 2 minutes Building Official
Wait for the permit to be released

 

Issuance of the Sign Permit 2 minutes Building Official