ABOUT THE SERVICE
A Certificate issued by the Building Official to the owner/applicant as a requirement for the installation of power lines to a building/structure and certifies the completeness of the installation of all electrical wirings.
CLIENT GROUP General Public
REQUIREMENTS ->Photocopy of the Building Permit (Wiring Permit)
->Certificate of Electrical Inspection to be accomplished
by an Electrical Engineer/Master Electrician
->Certificate of Fire Safety
FEES/PAYMENT REQUIRED Assessed by Building official
SERVICE SCHEDULE Monday to Friday
8:00 am – 5:00 pm
TOTAL PROCESSING TIME 8 minutes
PROCESS OF AVAILING THE SERVICE
STEPS INVOLVED
|
ACTIONS OF THE OFFICE OF THE MUNICIPAL ENGINEER
|
TRANSACTION TIME |
PERSON/S RESPONSIBLE |
Submit the complete requirements
|
Evaluates and processes the requirements and assessed fee | 1 minute | Engineering Personnel |
Proceed to the Office of the Municipal Treasurer for payment
|
(Staff of the Office of the Municipal Treasurer receives the payment and issues Official Receipt) | 3 minutes | Revenue Collection Clerk/Staff |
Present the OR to the Building Official
|
Documents and OR will be recorded | 2 minutes | Building Official |
Wait for the release of the CFEI
|
Issuance of the Certificate | 2 minutes | Building Official |