ABOUT THE SERVICE
An Electrical Wiring Permit is a requirement for installing, replacing, removing, connecting, disconnecting or repairing electrical works except replacing fuses, receptacles, switches and utilization equipment. On the other hand, a Certificate of Electrical Completion formally marks the completion of the project where the electrical inspector had inspected and agreed with the proper installation of electrical wirings.
CLIENT GROUP General Public
REQUIREMENTS ->Barangay Clearance
->Lot Owner’s Consent if lot is not owned by the applicant
->Photocopy of TCT
->Photocopy of the latest Real Property Tax Receipt
->Affidavit from the Mayor’s Office if the lot is a government property
->Waiver to be notarized if the lot is not owned by the applicant
->Electrical plans
->Duly accomplished Wiring Permit Form
FEES/PAYMENT REQUIRED For Residential Application & Business Application
->Application fee
->Building fee
->Electrical fee
->Plumbing fee
->Inspection fee
SERVICE SCHEDULE Monday to Friday
8:00 am – 5:00 pm
TOTAL PROCESSING TIME 43 minutes
PROCESS OF AVAILING THE SERVICE
STEPS INVOLVED
|
ACTIONS OF THE OFFICE OF THE MUNICIPAL ENGINEER
|
TRANSACTION TIME |
PERSON/S RESPONSIBLE |
Accompany the Electrical Inspector in the inspection of the site/project | Conducts inspection | 20 minutes | Engineering personnel |
Submit the complete requirements and accomplish the Wiring Permit Form | Processes and evaluates the correctness of the requirements and assess the fees | 10 minutes | Engineering Personnel |
Proceed to the Office of the Municipal Treasurer for payment | (Staff of the Office of the Municipal Treasurer receives the payment and issues Official Receipt) | 3 minutes | Revenue Collection Clerk/Staff |
Present the OR to the Building Official | Documents and OR will be recorded | 5 minutes | Building Official |
Wait for the release of the Electrical Wiring Permit | Issues the Electrical Permit | 5 minutes | Building Official |